Active Vehicle Barrier Installation

Active Vehicle Barrier Installation

Fortified Electrical Infrastructure for Fort Sill, OK Military Base


Project Overview

Precision & Protection at a Strategic Entry Point

J2 Company was selected as the design-build electrical partner for a high-security access control upgrade at Fort Sill’s Apache Gate. Working under USACE, our team delivered a full-scope electrical installation of four certified K12/MSO-P1 rated denial finger wedge barriers, integrating power infrastructure, control systems, safety components, and low-voltage technology to secure multiple base entry points.

The project required seamless coordination of design, construction, and system integration. J2 provided engineering support, site plans, and electrical drawings to guide UPS and control system installation. From conduit and wiring to barrier programming and alarm systems, every element was executed in strict accordance with USACE and military standards.

Scope of Work

Barrier Infrastructure & Foundation

  • Excavation for wedge barrier foundations
  • Installation of rebar and concrete for barrier bases
  • Placement of concrete from foundation through finished roadway
  • Concrete pads for Electronic Power Units (EPUs)

Electrical & System Integration

  • Conduit, wiring, and electrical connections from each barrier to its EPU
  • Power distribution to master control panel and subsystems
  • Installation of lighting, signage, poles, signals, and audible alarms
  • Low-voltage wiring for full control system connectivity
  • Drainage installation to support long-term system performance

Controls & Technology

  • Programming and operational setup of control panels
  • Overspeed and wrong-way vehicle detection systems
  • Installation of four saw-cut quadrupole inductive loop detectors per barrier
  • EFO (Emergency Fast Operation) buttons at guard booths and overwatch pads
  • Doppler radar installation for Overspeed and Wrongway Detection System
  • Master control panel installation in prefabricated command and control booth

Results

  • All wedge barriers installed with full functionality
  • Electrical systems tested and verified for reliability under operating conditions
  • Integrated control panel programming with EFO response and traffic detection
  • Successfully completed as part of a collaborative design-build effort with USACE
  • Successful Performance Verification Test (PVT) with recognition from USACE on professional and knowledgeable on-site team

Let’s Build What’s Next

Looking for an experienced electrical partner for your secure infrastructure or defense facility? J2 Company delivers precision electrical work and systems integration on time, on spec, and to the highest standard.

Contact J2 today

Client

U.S. Army Corps of Engineers (USACE)

Role

Design-Build Electrical Partner / Subcontractor

Timeline

N/A

Location of Project

Fort Sill, Oklahoma Military Base